Crane Accident – Dropped Load
Major Crane Accident – Dropped Load
Several hundred three tonne pre-cast concrete reinforced floor panels had been craned and installed into a multi story building without any obvious safety issues, when a panel detached from the basketed flat sling arrangement and fell to and shattered on the reinforced concrete floor below.
Many employees and subcontractors were in the vicinity of the falling load and resulting shrapnel – fortunately no-one was injured.
If the incident had occurred after March 2022 it would have been designted as a dangerous incident and reported to the Regulator. This was not a requirement under the previous WA OHS ACT 1994.
The slings had not failed, it was obvious that one sling had slipped towards the centre of the load allowing the load to slip out of the supporting flat slings.
This is a story of successive human and organisation errors, which resulted in the event and is about the knowledge, reliance and application of friction to secure lifting slings to loads and questionable engineering design.
The attached video supplied by the Department of Mines, Industry Regulation and Safety – Western Australia on “Friction” relates to this incident. https://vimeo.com/108303043
Details
- Location of and installation of lifting points on the panel and lifting configuration was not specified by the designer, it was left up to the rigging crew to decide. This appears to have constituted of breach of the WA WHS Regulation R 61 – Duties of Designers etc.
- The surface of the panel had a shiny finished surface and rounded chamfered edges where the slings made contact.
- Two flat slings in a basketed arrangement were used to lift the panel. The slings were not “choked” around the load and primarily made contact with the smooth underside of the panel.
- The flat slings had a protective “heavy duty” plastic sleeve to prevent the sling being cut by sharp edges. We now had a “Smooth” on “Smooth” contact surface between the slings and load.
- The flat slings were attached to a four-legged chain configuration which were attached to the crane hook.
- The flat slings were not supported in a vertical orientation by the lifting chains but were oriented at an angle to the load contact surface – see attached DMIRS video as an example of the sling angle of attack.
- This resulted in the flat sling not making full contact with the load surface – with the outside leading edge of the sling taking up the load and the inner edge of the sling taking up little to no load. Due to the angle of attack – a force was being applied to each sling, which tended to pull the slings into the middle of the load.
- Several hundred panels were rigged in this fashion and craned into place. The rigging and crane crew were comfortable with this arrangement as nothing had previously happened and there were no direct indicators of potential trouble.
- As the lifting chains were heavy to manage, it was decided to use a lighter weight and shorter set of chains, as it was determined that this would make it easier for the rigging crew to manage the lifts. The shorter set of chains decreased the flat sling angle of attack between the sling and load, increasing the force pulling the slings into the centre of the load.
- We now had a “Smooth” on “Smooth” basketed flat sling in a non-choked rigging configuration with an increased horizontal force on the slings due to the use of shorter lifting chains. It was a “Hair Trigger” situation, waiting for a slight change in circumstances.
- Several panels had been lifted using the different rigging configuration when “Bang” it all happened during a crane lift, one of the flat slings slipped and the load fell out of the slings to the level below.
There are several obvious points in this sequence of events, where human intervention would have prevented the incident from occurring.
Digital Construction Technology
The author recently published an article on LinkedIn titled “Positioning Loads, Look Mum, No Hands No Tag lines” , discussing the Australian Roborigger and Verton Load Positioning systems.
It is apparent that use of these types of smart remote control systems to position and install hundreds of pre-cast panels would have resulted in significant decrease in construction times resulting in decreased costs and eliminating the risk of personnel having to be near or under load load at the same time.
In this case – the construction contractor and the client had luck on their side – but Ignorance of Risk and reliance on “Good Luck” is no longer an acceptable option.